Over Hauling Of Boiler & Boiler Auxiliaries

Details of Over hauling of Boilers & their Auxiliaries


Work of Complete Overhauling of Boiler Pressure Part, Air Pre – heater for Unit 1 to 4 & coal Burner for Boiler Unit 1 to 3 [ 2 X 70 MW & 2 X 75 MW ] at GSECL-Kutch Lignite Thermal Power Station in the year of August 2015. (Kutch – Gujarat)

Work of removing of damaged vortex finder assembly from cyclone, erection of new assembly of vortex assembly in LHS cyclone at KLTPS unit # 04 (75 MW) GSECL-Kutch Lignite Thermal Power Station in the year of September 2015. (Kutch – Gujarat).

Work or repairing/replacement of water wall, economizer, CBD line, SCW LTSH, Arch lines/Extended water wall/roof tube, goose neck tubes, PSH and FSH boiler tubes by providing spool piece, bend etc. in boiler Unit # 3 (75 MW) at GSECL, Kutch Lignite TPS, Panandhro-Kutch in the year of August, 2015. (Gujarat-India)

Work of basket replacement and overhauling work of Air Pre-heater in boiler unit#3 (75 MW)at GSECL, Kutch Lignite TPS, Panandhro-Kutch in the year of August, 2015. (Gujarat-India)

Work of removing, repairing/re-strengthening/replacement, servicing and re-fitting of coal compartment assembly from inside in boiler unit # 3 (75 MW) at GSECL, Kutch Lignite TPS, Panandhro-Kutch in the year of August, 2015. (Gujarat-India)

Work of (8X135MW CFBC Boiler) APH Tube Replacement work of Unit # 6 at JSW, Raj west Power Ltd. (Barmer - Rajasthan) in the year of August , 2015.

Work of (8X135MW CFBC Boiler) Annual Boiler Overhauling Contract of Unit #6 at JSW, Raj west Power Ltd. (Barmer - Rajasthan) in the year of August 2015.

Work of Erection, commissioning and dismantling of Cup-lock type scaffolding inside the furnace up to coal burner area in boiler unit # 3 (75 MW)at GSECL, Kutch Lignite TPS, Panandhro-Kutchh in the year of August, 2015. (Gujarat-India)

Work of (8X135MW CFBC Boiler) APH Tube Replacement work of Unit # 2 at JSW, Raj west Power Ltd. (Barmer - Rajasthan) in the year of May , 2015.

Servicing of PA Fans 330 MW Unit # 3 at Adani Power Limited, Mundra Thermal Power Project, Dist. : Kutch (Gujarat). in the year of 2014.

Work of (8X135MW CFBC Boiler) Annual Boiler Overhauling Contract of Unit #3 at JSW, Raj west Power Ltd. (Barmer - Rajasthan) in the year of November 2013.

Work of (2X125MW CFBC Boiler) Annual Boiler Maintenance Contract of Unit #1 at Gujarat Mineral Development Corporation Ltd. (Contract through Korea Plant Services & Engineering Co. Ltd.) at Akrimota Thermal Power Station in the year of June 2013.

Work of (2X125MW CFBC Boiler) Annual Boiler Maintenance Contract of Unit #2 at Gujarat Mineral Development Corporation Ltd. (Contract through Korea Plant Services & Engineering Co. Ltd.) at Akrimota Thermal Power Station in the year of August 2013.

Work of Complete Overhauling of Boiler Pressure Part, Air Pre – heater for Unit 1 to 4 & coal Burner for Boiler Unit 1 to 3 [ 2 X 70 MW & 2 X 75 MW ] at GSECL-KLTPS (Kutch – Gujarat)in the year of 2012.

Dismantling & erection work of (4x125 MW CFBC Boiler) Cyclone Vortex Finders of Unit No. 2 at GIPCL, Surat Lignite Power Plant-Naninaroli in the year of December, 2011. (Gujarat-India)

Dismantling & erection work of (4x125 MW CFBC Boiler) Cyclone Vortex Finders of Unit No. 1 at GIPCL, Surat Lignite Power Plant-Naninaroli in the year of August, 2011. (Gujarat-India)

Work of replacement of H.P/L.P valves & 70 MW CFBC Boiler tubes on Boiler unit # 2 at GSECL, Kutch Lignite TPS, Panandhro-Kutchh in the year of August, 2011. (Gujarat-India)

Work of replacement of H.P/L.P valves & 70 MW CFBC Boiler tubes on Boiler unit # 1 at GSECL, Kutch Lignite TPS, Panandhro-Kutchh in the year of July, 2011. (Gujarat-India)

Work of replacement of H.P/L.P valves & 75 MW CFBC Boiler tubes on Boiler unit # 3 at GSECL-Kutch Lignite TPS, Panandhro - Kutchh in the year of April, 2011. (Gujarat-India)

Work of cutting, erection & welding of super heater safety valve in CFBC Boiler unit # 4 at GSECL-Kutch Lignite TPS, Panandhro-Kutchh in the year of February, 2010. (Gujarat-India)

Work of replacement of H.P/L.P valves & 70 MW CFBC Boiler tubes on Boiler unit # 2 at GSECL-Kutch Lignite TPS, Panandhro-Kutchh in the year of February, 2010. (Gujarat-India)

Dismantling & erection work of (2x125 MW CFBC Boiler) Cyclone Vortex Finders of Unit No. 1 of Gujarat Mineral Development Corporation Ltd. at Akrimota Thermal Power Station-Kutchh in the year of July, 2009. (Gujarat-India)

Dismantling, Fabrication and replacement of damage cyclone shell plate in unit 1 & 2 (2x125 MW CFBC Boiler ) of GIPCL, Surat Lignite Power Plant at Nani Naroli in the year of December, 2008.

Ducts repair work and MEJ to NMEJ conversion in 2x125 MW CFBC Boiler of GIPCL, Surat Lignite Power Plant at Nani Naroli in the year of November, 2008.

Assembly work of PA & SA Fan of GSECL at KLTPS Panandhro-Kutch in the Year of In them Year of September, 2008.

Dismantling work of PA Fan impellors & dismantling of shaft from impellors Assembly of SA Fan of GSECL at KLTPS Panandhro-Kutch in the Year of In the Year of August, 2008.

MEJ/NMEJ/Duct/Dampers/Gate maintenance work in 2x125 MW CFBC Boiler of GIPCL, Surat Lignite Power Plant at Nani Naroli in the year of April, 2008.

ESP repair work in 2x125 MW CFBC Boiler of GIPCL, Surat Lignite Power Plant at Nani Naroli in the year of April, 2008.

Overhauling of Burners & Burner Station Valves of 70MW Unit No.1 at Gujarat State Electricity Corporation Ltd., KLTPS Panandhro-Kutch (Gujarat –India) in the year of December 2005.

Over Hauling of CW Pump in unit no I, II&III at K.L.T.P.S. Panandhro of Gujarat Electricity Board in year of 2001.

Over hauling of B.F.P. Partial Unit II & I in 70 MW BHEL make T.G. Set at K.L.T.P.S. Panandhro of Gujarat Electricity Board in the year of 1999.

Awarding Contract for Overhauling of Burners of Boiler Unit no 4,5, & 6 at TPS Wanakbori of Gujarat Electricity Board in the year of 21 July 1992 to 20 July 1993.

Preparation of Surface of Boiler Tubes of Unit 1 & 2.at T.P.S. Wanakbori of Gujarat Electricity Board. In the year of May 1992.

Repair/rectification replacement of HRH/CRH/LTSH coil of Boiler#6 at T.P.S. Wanakbori of Gujarat Electricity Board. In the year of Feb 1992.

Repairing/rectification of expansion joints of flue gas and Air ductings of Boiler#4 at T.P.S. Wanakbori of Gujarat Electricity Board. In the year of August 1992.

Repairing/rectification of expansion joints of flue gas and Air ductings of Boiler#5 at T.P.S. Wanakbori of Gujarat Electricity Board. In the year of August 1992.

Repairing/rectification of expansion joints of flue gas and Air ductings of Boiler#6 at T.P.S. Wanakbori of Gujarat Electricity Board. In the year of August 1992.

Replacement of seals, its supporting Tee Bars Baskets etc. of APH 3B at TPS Wanakbori of Gujarat Electricity Board in the year of 1991.

Dismantling/removal and reversing & re-erection of theating elements/baskets of the top layer of the coal end of air preheater of Boiler Unit#4 at T.P.S. Wanakbori of Gujarat Electricity Board. In the year of December 1991.

Repairing/rectification of expansion joints of flue gas/air ducting of boiler unit no.3 at T.P.S. Wanakbori of Gujarat Electricity Board. In the year of September 1991.